Nerida Hansen - Developer Feature Breakdown



Notes:
  • Additional iOS dev resource for an early launch 


Actual Schedule
Notes
Client payment
Aug 13

Internal Team Onboarding Date
Aug 13
deployed on the day of payment
Dev Start Date / Project Intro (Unpacking Part 1)  
Aug 17

Kick-off (Unpacking Part 2)
Aug 24

Development Timeline
Aug 17 - Sep 16 (Sep 20)  
Sep 17 - Oct 16
Oct 17 - Nov 16
added 2 working days to cover the holidays
MVP Launch
Original: Jan 2022
Adjusted (due to additional resource allocation): end of Nov or Dec 2021
excluding optional items in Roadmap


Month 1

Feature
Scope
Workload Estimate
Mobile Setup
Mobile layouts, menus, and navigation, as well as setting you up with Apple and Google developer accounts.
8 days - Baseplate Setup
Server Setup
Backend and server setup as well as a login system for the super administrator to access the Content Management System (CMS).

Email / SMS Verification & OTP Service
The ability to send emails via the system and verify user phone numbers and emails. By default we use Mandrill.

User Accounts 
Login, Logout, Forgot Password, SignUp

Designer Onboarding
Name, Location, Photo
2 days
Buyer Onboarding
Name, Work, Company
2 days
User Profile & Accounts
This includes edit info, about, account settings. 

Terms of Service & Privacy Policy
Note: We will only set up the technical ability for you to add and manage these. You don't need to have them prepared yet. 

Manage Users (Admin CMS)
Admins must be able to add, edit, and remove users. 

Manage Industry Categories & Company Types (Admin CMS)
Admins must be able to add, edit, and remove industry categories & company/team types. 
1 day
Home Tab - Designer
This includes Edit Profile, Upload Product & Feed.

Excluding Share Profile, Copy Link, View Archive
4 days
Upload a Product - Designer
Designers can upload single designs. Includes drag and zoom to crop (available in baseplate)

Excluding Multiple designs Upload/Collection, Tags

Important Note: Upload will support multiple design/collection by Month 4, must consider in the design and backend implementation.
5 days 
View Product Detail - Designer
View product info, # of views, # of likes. Includes edit & delete functions.

Excluding Archive, Share, Copy Link

Important Note: Product will have multiple design/collection by Month 4, must consider in the design and backend implementation.
5 days


Total: 27


Month 2