Heater test in vacuum
Plan of the heater test in vacuum.
  R. Takahashi

Control sequence
  • Set temperature is changed by 2 deg. and kept in one hour.

Monitor channel
  • GAS LVDT (F0, F1, F2, F3, BF)
  • BF damper (V)
  • BF temperature

Note
  • DC control for GAS filters is off.